Temporary Suspension of Power Supply in the Engineering Building for 24 Scheduled Times Due to Replacement of High- and Low-Voltage Equipment (Please be informed).

1. Engineering Building Power Outage Schedule:
(1) August 30, 2025 (Saturday), 8:00 a.m. – 7:00 p.m.: Complete power outage of general and emergency power (including elevators).
(2) September 20, 2025 (Saturday), 8:00 a.m. – 7:00 p.m.: Power outage of general lighting and outlets on Floors 1–4.
(3) November 1, 2025 (Saturday), 8:00 a.m. – 7:00 p.m.: Complete power outage of general lighting and outlets.
(4) November 8, 2025 (Saturday), 8:00 a.m. – 7:00 p.m.: Complete power outage of general lighting and outlets.
(5) November 22, 2025 (Saturday), 8:00 a.m. – 7:00 p.m.: Power outage of general 220V circuits on 1F to B2 (including air conditioning and laboratory equipment).
(6) November 29, 2025 (Saturday), 8:00 a.m. – 7:00 p.m.: Power outage of general 220V circuits on 1F to B2 (including air conditioning and laboratory equipment).
(7) December 13, 2025 (Saturday), 8:00 a.m. – 7:00 p.m.: Power outage of general 220V circuits on B1–B2 (including air conditioning and laboratory equipment).
(8) December 20, 2025 (Saturday), 8:00 a.m. – 7:00 p.m.: Power outage of general 220V circuits on B1–B2 (including air conditioning and laboratory equipment).
(9) February 8, 2026 (Sunday), 8:00 a.m. – 7:00 p.m.: Complete power outage of general 220V lighting circuits.
(10) February 14, 2026 (Saturday), 8:00 a.m. – 7:00 p.m.: Complete power outage of general 220V lighting circuits.
(11) April 25, 2026 (Saturday), 8:00 a.m. – 7:00 p.m.: Complete power outage of emergency 220V circuits.
(12) May 2, 2026 (Saturday), 8:00 a.m. – 7:00 p.m.: Complete power outage of emergency 220V circuits.
(13) May 16, 2026 (Saturday), 8:00 a.m. – 7:00 p.m.: Power outage of general lighting and outlets on 1F to B1.
(14) May 23, 2026 (Saturday), 8:00 a.m. – 7:00 p.m.: Power outage of general lighting and outlets on 1F to B1.
(15) June 13, 2026 (Saturday), 8:00 a.m. – 7:00 p.m.: Complete power outage of emergency 220V circuits (including lighting and laboratory equipment).
(16) June 20, 2026 (Saturday), 8:00 a.m. – 7:00 p.m.: Complete power outage of emergency 220V circuits (including lighting and laboratory equipment).
(17) July 4, 2026 (Saturday), 8:00 a.m. – 7:00 p.m.: Complete power outage of general 220V circuits (including air conditioning and laboratory equipment).
(18) July 11, 2026 (Saturday), 8:00 a.m. – 7:00 p.m.: Complete power outage of general 220V circuits (including air conditioning and laboratory equipment).
(19) August 1, 2026 (Saturday), 8:00 a.m. – 7:00 p.m.: Complete power outage of emergency lighting and outlets.
(20) August 8, 2026 (Saturday), 8:00 a.m. – 7:00 p.m.: Complete power outage of emergency lighting and outlets.
(21) August 22, 2026 (Saturday), 8:00 a.m. – 7:00 p.m.: Complete power outage of general circuits.
(22) August 29, 2026 (Saturday), 8:00 a.m. – 7:00 p.m.: Complete power outage of general circuits.
(23) September 19, 2026 (Saturday), 8:00 a.m. – 7:00 p.m.: Complete power outage of emergency power (including elevators).
(24) September 26, 2026 (Saturday), 8:00 a.m. – 7:00 p.m.: Complete power outage of emergency power (including elevators).

2. Contact Information:
(1) Construction and Maintenance Section: Mr. Ting, Ext. 5165, Mobile 0984-262-343; Mr. Su, Ext. 5599, Mobile 0984-262-033.
(2) Supervising Unit (Electrical & Mechanical Section): Mr. Chang, Ext. 3051, Mobile 0987-673-515; Mr. Chou, Ext. 3051, Mobile 0911-375-270.
(3) Contractor (Nan Ya Power Distribution Panel Co.): Mr. Chen, Mobile 0965-619-969.
(4) Security Section: Ext. 5000.

Contact person:Tommy
Contact number:409-5165